Risk Tasks

Note

Required role: developer, compliance_manager, manager or account_admin Required license feature: risks

A risk is worked off through countermeasures (what you do about it) and tasks (the concrete steps, with an owner and a due date). The Tasks tab lists all tasks of the risks in one project or module.

Countermeasures

Open a risk, then the Countermeasures tab, and click Add countermeasure.

Field Description
Name 3 to 200 characters, for example Use parameterised queries for all DB access.
Status identified, planned, completed, ok, required, not-required or verified.
Comment Free text.
Responsible One or more users.
Risk reduction (%) 0 to 100.
Standard reference For example OWASP-ASVS V5.3.4.
Validation method How you prove it works.
OTM mitigation ID Links the countermeasure to a threat-model mitigation.

Save and Create new one keeps the dialog open for the next entry. The trash button removes a countermeasure.

Tasks

On the risk's Tasks tab, click Add task. The Add a task dialog has these fields:

Field Description
Countermeasure Required. The task belongs to it.
Name Required. What has to be done.
Status backlog, planned, in_progress, in_review or completed.
Due date A day, counted in UTC.
Frequency Free text such as quarterly.
Comment For example Re-check after each release.
Responsible One or more users.

Each task row also offers Create issue, which opens a GitHub issue from the task, and View issue once it exists. Without a GitHub integration, or when the project or module has no repository set, the link reads Copy details and copies the task text to the clipboard.

The Tasks tab

  1. Open Risks → Tasks.
  2. Choose a project or module at the top right (Select report target). Until you do, the page only asks you to select a project.
  3. Read the tiles: total, upcoming (due within 7 days), overdue, opened (planned, in progress or in review), resolved and exceptions ending in 30 days.
  4. Use the buttons Backlog, In progress and Completed to show or hide groups, and the selector My tasks, Unassigned or All tasks.

A task is overdue when it is not completed and its due date lies before today. Overdue tasks carry (overdue) after the date and a coloured row. A task due today is not yet overdue.

The Tasks tab for All module of boostME with the tiles total, upcoming, overdue, opened, resolved and exceptions ending in 30 days, the Backlog, In progress and Completed buttons, All tasks selected, and one task due Oct 1, 2026 marked as overdue.

Reminders

  • When a task becomes overdue, its responsible users receive one message and one e-mail.
  • 14 days before a temporary exception ends, the decision maker and the responsible users are notified once.

Each reminder is sent at most once per event: a task whose due date is moved and missed again, or an exception that is renewed, is reminded again. If sending fails, it is logged and not repeated. Users are only notified if they hold a role in the company. The check runs regularly in the background (by default every hour).